Every number on Measured Yard comes from the formulas and data on this page. If your supplier's numbers differ, trust theirs: material weights vary by quarry and moisture.

The basic formula

Volume = area × depth. We add your waste allowance, then convert to the units the material is sold in: cubic yards or cubic meters for bulk, tons or tonnes for stone and sand, and whole bags or pieces for everything else.

All math runs in metric internally using exact conversion factors (1 ft = 0.3048 m, 1 cubic yard = 0.764555 m³, 1 short ton = 907.185 kg), then converts back to your units.

Concrete bag yields

BagConcrete it makesSource
40 lb0.30 cu ftManufacturer product data
50 lb0.375 cu ftManufacturer product data
60 lb0.45 cu ftManufacturer product data
80 lb0.60 cu ftManufacturer product data
25 kg11.7 LSame yield density as the 80 lb bag
40 kg18.7 LMatches about 19 L stated on European bags

Material weights

Typical loose weights, as delivered. Wet material is heavier.

Materiallb per cu ydkg per m³
Crushed stone (#57)2,7001,600
Pea gravel2,8001,660
Crusher run3,0001,780
Decomposed granite2,8001,660
River rock2,7001,600
Lava rock1,200710
Concrete or paver sand2,9001,720
Play or mason sand2,7001,600
Topsoil2,2001,300
Fill dirt2,4001,420
Garden soil mix1,600950
Compost1,100650

Compaction, waste and rounding

  • Compacted bases (under pavers and walls) use 20% more gravel than the finished depth, because compaction squeezes the stone together.
  • Waste allowances are yours to change. Our defaults: 5% for mulch, gravel and sod, 10% for concrete, soil and deck boards.
  • Counts round up: bags, pavers, blocks, posts and boards. Bulk orders round up to the next half yard, half m³, half ton or half tonne, the way yards sell them.
  • Pavers are counted from nominal sizes, which already include the joint. Laying patterns add 5% (straight), 10% (herringbone) or 15% (curves).

Lawns

Seeding rates are the middle of university extension ranges for a new lawn, and half that for overseeding. Sod rolls are 10 sq ft (US) or 1 m² (metric); pallet sizes vary by farm, so you can choose yours.

What we do not calculate